Professional services provided
Projects and work supervisions in the south of Italy
Regione Basilicata
- CONSORZIO DI BONIFICA BRADANO E METAPONTO - (MT)
1. Scanzano, Policoro and Nova Siri Irrigation Network Construction
| Year |
Task |
Stage |
Details |
| 1958 |
Design and consultancy |
Constructed |
Prefabricated buildings |
2. Metaponto Plain Full Pipes Irrigation Network Upgrading (8.000 Ha)
| Year |
Task |
Stage |
value of works |
Details |
| 1979 |
Preliminary design |
Approved |
It. Lire 90 b |
Irrigational area: Ha 8.000 |
| 1983 |
Detailed design |
|
It. Lire 45 b |
Clients: Maggiò, Zecchina and other contractors |
3. Sinni Aqueduct Irrigation Network Upgrading.
| Year |
Task |
Stage |
value of works |
Details |
| 1978-86 |
Detailed designs and consultancies |
Constructed and operative |
|
|
Project implementation details:
3.1. Sinni Aqueduct irrigation network.
Detailed design and working plan; Client: building contractors.
Consorzio Metaponto 1): area A, districts 1, 3 e 4 across 4.500 Ha; 1978-80
Operative.
3.2. Draining pump irrigation networks upgrading
Consultancy; 1983-86
3.3. Sinni Aqueduct irrigation network connections upgrading ("white" areas).
Consultancy and project; 1979-83.
- CONSORZIO DI BONIFICA DELL'ALTA VAL D'AGRI - (PZ)
1. Pertusillo Aqueduct - Downhill Area
| Year |
Task |
Stage |
value of works |
Details |
| 1984 |
Detailed design |
Constructed and operative |
It. Lire 15 b |
Pipes: DN 1400-1200 mm; Length: km 15 |
2. "High" Pertusillo irrigation aqueduct - Uphill Area
| Year |
Task |
Stage |
value of works |
Details |
| 1984 |
Detailed design |
To be examined |
It. Lire 10 b |
|
3. Management and Expansion of Agri Medium Hight Valley Irrigation Network.
| Year |
Task |
Stage |
value of works |
Details |
| 1987 |
Detailed design |
Constructed and operative |
It. Lire 10 b |
|
Regione Calabria
- MINISTERO LL.PP. PROVVEDITORATO DI CATANZARO
1. Noce River's Basin Plan
| Year |
Task |
Stage |
value of works |
Details |
| 1990-92 |
Designs |
Tested in 1993 |
|
Together with Società Lotti and Studio ing. D'Alessandro (PA) |
- CONSORZI DI BONIFICA RAGGRUPPATI DI CATANZARO (CZ)
1. Alli-Tacina Area Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1973-76 |
Consultancy for the project upgrading and work supervision |
Constructed and operative |
|
Irrigational area: Ha 5,000 |
2. Isola Capo Rizzuto Plateau Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1975-78 |
Detailed design |
Constructed and operative |
It. Lire 45 b |
Irrigational area: Ha 11,000 |
Value of works - details
lot I : It. Lire 6.148.000.000;
lot II : It. Lire 9.032.000.000:
lot III: including draining network management It. Lire 12,993 bilion;
lot IV: including draining network management Italian Lire 13,587 bilion.
3. Crocchio Stream Intake Work
| Year |
Task |
Stage |
value of works |
Details |
| 1975 |
Design, consultancy |
Constructed and operative |
It. Lire 362 m |
|
4. Amato Stream Outlet Canal Consolidation
| Year |
Task |
Stage |
value of works |
Details |
| 1978 |
Consultancy |
Constructed and operative |
It. Lire 45 b |
Client: Farsura |
5. Savuto Coastal Plain Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1974 |
Detailed design, consultancy for the water works |
Constructed and operative |
It. Lire 45 b |
Irrigational area: Ha 1,200 |
6. Tacina and Cape Rizzuto Valleys Irrigation Networks - Soleo Stream Intake and Conduction Works
| Year |
Task |
Stage |
value of works |
Details |
| 1974 |
Detailed design, consultancy for the water works |
Constructed and operative |
It. Lire 1,907 b |
Discharge: 2 mc/s |
7. Alli-Tacina River Coastal Plain Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1974 |
Detailed design, consultancy for the work supervision |
Constructed and operative |
It. Lire 4,8 b |
Irrigational area: Ha 5,000 |
8. S. Eufemiada Coastal Plain Irrigation on Savuto River
| Year |
Task |
Stage |
value of works |
Details |
| 1974 |
Detailed design, consultancy for the work supervision |
Constructed and operative |
It. Lire 2,755 b |
Irrigational area: Ha 1,200 |
9. Pesipe Stream's Bed Management and Area Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1980-91 |
Preliminary design |
|
|
Team work |
10. Catanzaro District's Coastal Area Irrigation - Valle Tacina, Isola Capo Rizzuto, Alli-Tacina and Tacina-Copanello Irrigation and Remote Control System Completion
| Year |
Task |
Stage |
value of works |
Details |
| 1984-87 |
|
|
It. Lire 5 b |
|
Project Implementation Details:
10.1. Isola Capo Rizzuto irrigation and remote control system completion (€ 2.600.000, 00)
Detailed design; 1998
Project security coordination 1999;
Test to be completed.
11. Angitola and Melito Dams: Flood Risk Studies(DAMBREAK)
11.1 DAMBREAK Angitola: 1998
11.2 DAMBREAK Melito: 2006
12. Alli-Tacina and Alli-Copanello Irrigation System
| Year |
Task |
Stage |
value of works |
Details |
| 2001-06 |
Detailed designs, studies |
|
ε 22 m |
Works: weirs, intake works, Simeri river desilting basin (320,000 m3) |
Project Implementation Details:
12.1 Detailed design: 2001-2002.
12.2 Environmental impact analysis: 2003.
12.3 Working lot at 152 a.s.l. - detailed design: 2003-2004;
value of works € 14 milioni; tendered for in 2004 and under construction.
12.4 Completion lot at 119 a.s.l. - detailed design: 2005;
Value of works € 6 m; to be examined by SIIT (nov. 2006).
- CONSORZIO DI BONIFICA DELLA VALLE DEL LAO - (CS)
1. River Lao's Left Bank Area Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1968 |
Work direction, consultancy for the detailed design |
Constructed and operative |
|
Irrigational area: Ha 1,000 |
2. River Lao's Right Bank Area Irrigation and System Upgrading
| Year |
Task |
Stage |
value of works |
Details |
| 1970 |
Works direction, detailed design |
Constructed and operative |
It. Lire 1 b |
Irrigational area: Ha 700 |
3. River Lao Weir (1 bilion)
| Year |
Task |
Stage |
value of works |
Details |
| 1970-72 |
Detailed design, consultancy for the works |
Constructed and operative |
|
|
4. Abatemarco stream Irrigation System
| Year |
Task |
Stage |
value of works |
Details |
| 1971 |
Detailed design |
|
It. Lire 1,6 b |
Irrigational area: Ha 700 |
Regione Campania
- CONSORZIO DI BONIFICA VELIA - (SA)
1. Palistro Irrigation Networks: Lots I and II
| Year |
Task |
Stage |
value of works |
Details |
| 1976-77 and 1986-89 |
Detailed design - consultancy for testing stage |
Constructed and operative |
It. Lire 2 b |
Irrigational area: Ha 600 |
2. Alento-Badolato Hills Irrigation Network
| Year |
Task |
Stage |
value of works |
Details |
| 1978 |
Detailed design, consultancy for the work supervision |
Constructed and operative |
|
Irrigational area: Ha 500 |
3. Alento Valley Irrigation
| Year |
Task |
Stage |
value of works |
Details |
| 1979-88 |
Detailed design |
Approved |
It. Lire 40 b |
Irrigational area: Ha 3,000 |
4. Alento River Management and Irrigation System.
Consultancies.
5. Badolato-Palistro Irrigation Scheme Completion and Remote Control System
Project: 1986-88.
- CONSORZIO FONDARIO DI VALLO DELLA LUCANIA - (SA)
1. Carmine Dam and Torna Stream Irrigation System
| Year |
Task |
Stage |
value of works |
Details |
| 1978 and 1982-88 |
Detailed design, consultancy for the work supervision |
Constructed and operative |
|
Irrigational area: Ha 1,000 |
2. Remote Control Management Training Course; 2 weeks; 1983.
- CONSORZIO AURUNCO DI DI BONIFICA - SESSA AURUNCA
1. Irrigation Network Expansion
| Year |
Task |
Stage |
value of works |
Details |
| |
consultancy |
|
|
Irrigational area: Ha 6,500 |
2. Irrigation network (Italian Lire 600 m; 1971) - consultancy and project.
| Year |
Task |
Stage |
value of works |
Details |
| 1971 |
Detailed design, consultancy |
|
It. Lire 600 m |
|
- CONSORZIO DI BONIFICA DEL SANNIO ALIFANO - (CE)
1. Volturno River Weir and Conduction Canal's First Reach
| Year |
Task |
Stage |
value of works |
Details |
| 1953-62 |
Design, work direction |
Constructed and operative |
It. Lire 1 b |
With Prof. Eng. F, Lotti |
2. Volturno's Right Bank Area Irrigation Expansion
| Year |
Task |
Stage |
value of works |
Details |
| 1960 |
Detailed design |
Constructed and operative |
It. Lire 1,2 b |
Irrigational area: Ha 1,100 |
3. Presenzano Plain Irrigation
Project Implementation Details:
3.1. Lot II - including canals (1.200 Ha - Italian Lire 600 m)
Detailed design; 1962;
Constructed and operative.
3.2. Lot III - sprinkling system (1.000 Ha - Italian Lire 1,5 billion)
Detailed design - work supervision consultancy; 1962-1976
Constructed and operative.
4. Volturno River's Left Bank Irrigation System Construction, Expansion and Development
4.1 - lot II - sub-lot I (distribution network).
Detailed design; client: Cidonio contractor; 1964.
Operative.
4.2 - lot IV, Gioia-S. Simeone districts (600 Ha) (Italian Lire 400 m)
Detailed design; 1968 -
Operative.
4.3 - lot V, Surge works for the uphill area (Italian Lire 300 m).
Detailed design; 1969 -
Operative,
4.4 - lot VI, Main distribution canal upgrading (Italian Lire 300 m.)
Detailed design and work direction; 1970
Operative.
5. Alifana plain uphill water management plan (Italian Lire 4 billion).
Preliminary design; 1969
6. Volturno river's left branches management
Detailed design and consultancy; 1972-76
Operative.
7. Volturno river's left branches management (It. Lire 3,5 b.)
Detailed design and consultancy; 1972-1976
Operative.
- IN.CO.MIR spa
Calore Irpino River Water Management
Preliminary design; 1988.
- SOC. ENRIN 2000 - Napoli
Hydroelectric Exploitation of Simeri, Savuto and Tronto Rivers Irrigation Canals
| Year |
Task |
Stage |
value of works |
Details |
| 1990-93 |
Feasibility design |
|
|
|
Regione Molise
- CONSORZIO DI BONIFICA IN SX TRIGNO E DEL SINELLO (CH)
1. Area Irrigation - General and Expansion Plan
| Year |
Task |
Stage |
value of works |
Details |
| 1951 |
Public works reliminary design |
Constructed and operative |
|
|
- CONSORZIO DI BONIFICA DEL BASSO MOLISE - (CB)
2. Low Molise Irrigation, with Water Conducion from Ponte Liscio Dam
| Year |
Task |
Stage |
value of works |
Details |
| 1962 |
Preliminary design |
Approved, partly constructed and operative |
It. Lire: 13 b |
With Prof. Arredi and eng. Scalfati.
Irrigational area: Ha 20,000 |
Regione Puglia
- CASSA PER IL MEZZOGIORNO - P.S. 14
1) Sinni Aqueduct Support Sructures
| Year |
Task |
Stage |
value of works |
Details |
| 1976 |
Consultancy |
Approved |
|
|
2) Pertusillo Aqueduct
| Year |
Task |
Stage |
value of works |
Details |
| 1976 |
Consultancy |
|
|
Consultancy for a reach of the aqueduct |
3) Sinni Basin Water Provision with Water Conduction from Sauro and Medio Agri Streams
Project implementation details:
3.1. Hydrological studies (streams Sauro and Medio Agri)
Preliminary design for Soc. SPEA; 1979
3.2. Detailed design of the whole plan and particularly of the intake and conduction works; works consultancy; Works direction of the reach granted to Del Favero - Maggiò group (It. L. 80 b); 1983-94
Partially operative.
4) Sinni aqueduct regulation work
| Year |
Task |
Stage |
value of works |
Details |
| 1983-86 |
Consultancy |
|
It. Lire: 36 b |
Client: Casmez Alta Sorveglianza |
5) Sinni Aqueduct
hydrological and hydraulic studies; 1983-84
6) Pertusillo Irrigational Aqueduct
Project implementation details:
6.1. Preliminary design of Agri valley area and high Metaponto plain water supply system (4,1 mc/s) - italian Lire 100 b - 1983;
6.2. Detailed design of lot I - It. L. 30 b - 1983
Application accomplished. A variant model realized and granted to the designer through Consorzio Alta Val d'Agri (see A.26)
- ANAS COMPARTIMENTO DI BARI
S.S. 106 Expansion - lot III
| Year |
Task |
Stage |
value of works |
Details |
| 1990-91 |
Hydraulic management |
Constructed and operative |
|
Client: Impresa Castelli |
- CONSORZIO DI BONIFICA DELL'ARNEO - NARDO' (LE)
1. Sinni Aqueduct and Sinni-Salento Irrigation Scheme
1.1. Sinni Aqueduct: Salento Irrigation Scheme, reach IV, 150.000 Ha, value of project It. Lire 3.100 m
Preliminary design, with prof. V. Cotecchia; 1979-1988
To be examined.
1.2. Sinni aqueduct: Salento irrigation scheme, reach IV, lot I (DN 3000 mm)
Detailed design, with prof. V. Cotecchia; 1981; It. L. 40 b
Operative.
1.3. Sinni aqueduct: Salento irrigation scheme, reach IV, Chidro spring surge works (2 mc/s)
Detailed design, with the Conzorzio's technical practice; 1982; It. L. 10 b
Operative.
1.4. Sinni-Salento irrigation scheme, lot I (F.I.O.)
Consultancy for the works, with prof. Cotecchia (It. L. 125 b)
Granted to Vianini contractor, Rome.
1.5. Sinni-Salento irrigation, lot II
Detailed design coordination and project with others (It. L. 140 b); consultancy for Sava basin and other works; (also with Impresa Vianini as client)
Operative.
1.6. Sinni-Salento irrigation, lot III
Detailed design coordination; project, with others (It. L. 150 b), consultancy
(also with Impresa Vianini as client)
Operative.
1.7. Sinni aqueduct: Salento irrigation scheme, Monteparano branch point (It. L. 3 b)
Detailed design, with Consorzio's technical practice; 1984
Operative.
- ENTE IRRIGAZIONE PUGLIA E LUCANIA - (BA)
Sinni Aqueduct: Montecotugno Dam
| Year |
Task |
Stage |
value of works |
Details |
| 1977-83 |
Work supervision |
Constructed and operative |
It. Lire 65 B - pipelines supply excluded |
Reach VI-V26 and Sinni-Agri; Valsinni tunnel; by pass
|
- CONSORZIO DI BONIFICA STORNARA E TARA - (TA)
1. Tara Area: S. Giuliano Dam Irrigation Scheme
| Year |
Task |
Stage |
value of works |
Details |
| 1969 |
Working plan |
Constructed and operative |
|
Client: Impresa Della Morte |
3. Sector VII S irrigation scheme with waters supplied by Sinni aqueduct
| Year |
Task |
Stage |
value of works |
Details |
| 1983 |
Detailed design |
To be examined |
|
Irrigational area: Ha 600 |
| 1984 |
Preliminary design |
|
|
Irrigational area: Ha 1,500 |
4. Palagianello and Gennarini Ravines Drainage System
| Year |
Task |
Stage |
value of works |
Details |
| |
Detailed design |
Approved |
It. Lire: 8 b |
Parcelled out in 3 lots |
5. Palagianello and Gennarini Ravines Area Management (Tara River's Outlet)
| Year |
Task |
Stage |
value of works |
Details |
| 1982-88 |
Preliminary design; hydrological study |
Programmatic plan approved with Law 183/89 |
It. Lire: 80 b |
|
- CONSORZIO DI BONIFICA CAPITANATA - (FO)
1. Muschiatura Marsh Land Reclamation
| Year |
Task |
Stage |
value of works |
Details |
| 1952 |
Detailed design |
It. Lire: 100 m |
|
With: Soc. SIAF |
2. Saccione Stream Management, lot I
| Year |
Task |
Stage |
value of works |
Details |
| 1960 |
Preliminary design |
|
It. Lire: 1 b |
With: Prof. Arredi |
- CONSORZIO DI IMPRESE METAPONTO 1 - P.S. 14 DELLA CASMEZ
1) Metaponto Area Irrigation Network - "A" districts 1, 3, 4, Water Supplied by Sinni Aqueduct
| Year |
Task |
Stage |
value of works |
Details |
| 1976 |
Detailed design |
Constructed and operative |
|
Irrigational area: Ha 4,500 |
2) Tara- Stornara area irrigation scheme, "C" zone
| Year |
Task |
Stage |
value of works |
Details |
| 1976 |
Design |
Approved |
It. Lire: 36 b |
Irrigational area: Ha 13,500 |
- ENTE RIFORMA PUGLIA E LUCANIA - (BA)
Taranto District Land Reclamation General Plan - Public Works
| Year |
Task |
Stage |
value of works |
Details |
| 1951 |
Preliminary design |
|
|
|
Regione Sardegna
- OPERE PUBBLICHE S.p.A. (CAGLIARI)
S. Elia Stadium's Car Park - Civil Engineering Works
| Year |
Task |
Stage |
Value of works |
Details |
| 1990 |
Detailed design |
Constructed and operative |
|
Area: Ha 20
Italia '90 World Football Championship |
- CONSORZI RIUNITI DELLA SARDEGNA MERIDIONALE - (CA)
1. Su Pauli Land Reclamation (Villamar)
| Year |
Task |
Stage |
Value of works |
Details |
| 1962 |
Design |
Constructed and operative |
It. Lire 60 m |
|
2. Villamar-Segariu Road
| Year |
Task |
Stage |
Value of works |
Details |
| 1966-74 |
Detailed design |
Constructed and operative |
It. Lire 300 m |
|
3 Pula Land Reclamation and Water Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1994 |
Detailed design |
Project included in Q.C.S. 2000-06's plan |
|
Area: Ha 5,000
|
4. Pula area irrigation, water supplied by Monte Nieddu basin
| Year |
Task |
Stage |
Value of works |
Details |
| 1993-95 |
Design |
|
It. Lire: 75 b |
Area: Ha 5,000
|
- CONSORZIO DI BONIFICA INTEGRALE LARINESE - (NU)
1. Cigno Stream Dam
| Year |
Task |
Stage |
Value of works |
Details |
| 1969 |
Preliminary design |
Approved |
|
With Scalfati, civil engineer |
1.1. Cigno Stream Dam
| Year |
Task |
Stage |
Value of works |
Details |
| 1978-91 |
Surveys, detailed design, work supervision |
Suspended |
|
With Scalfati, civil engineer |
2. Anacoreta Bridge on Biferno River
| Year |
Task |
Stage |
Value of works |
Details |
| 1970 |
Detailed design, work supervision |
Constructed |
It. Lire: 700 m |
|
4. Saccione Stream's Bed Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1983-91 |
Detailed design |
|
|
|
- CONSORZIO DI BONIFICA DEL BASSO SULCIS - (CA)
Sprinkler System Irrigation
| Year |
Task |
Stage |
Value of works |
Details |
| 1968 |
Detailed design |
Constreucted and operative |
It. Lire: 600 m |
Irrigational area: Ha 550 |
- CONSORZIO DI BONIFICA DEL CIXERRI - (CA)
1. Irrigation Scheme of Lot 1
| Year |
Task |
Stage |
Value of works |
Details |
| 1965 |
Consultancy |
Constructed and operative |
|
Irrigational area: Ha 4,500
Client: Gariazzo contractor |
2. Lot III Irrigation of Lot III with Waters Supplied by Medau Zirimilis Dam
| Year |
Task |
Stage |
Value of works |
Details |
| 1971 |
Preliminary design |
|
It. Lire: 5,4 b |
Irrigational area: Ha 4,500 |
- CONSORZIO DI BONIFICA DEL CAMPIDANO DI TERRALBA (NU)
1. Lot I: Irrigation, Land Reclamation and Roadway
| Year |
Task |
Stage |
Value of works |
Details |
| 1969 |
Work supervision |
Constructed and operative |
It. Lire: 600 m |
Irrigational area: Ha 600 |
2. Canal Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1970 |
Design, work direction |
Operative |
It. Lire: 250 m |
|
3. Rio Murta Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1970 |
Design, work direction |
Operative |
It. Lire: 130 m |
|
9. District II: Irrigation, Water Management, Roadway
| Year |
Task |
Stage |
Value of works |
Details |
| 1971-86 |
Detailed design |
Constructed and operative |
It. Lire: 29 b |
Area: Ha 3,500 With Scalfati, civ. Eng. and Sermonti, agronomist |
4. District II: Water Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1975 |
General plan, detailed design |
Operative |
It. Lire: 5 b |
|
- CONSORZIO DI BONIFICA DEL NUORESE - (NU)
1. Cedrino valley Irrigation: Central lot
| Year |
Task |
Stage |
Value of works |
Details |
| 1971 |
Preliminary design |
|
It. Lire: 5,5 b |
Irrigational area: Ha 3,000 |
1.1. Cedrino valley irrigation: lots I, II
| Year |
Task |
Stage |
Value of works |
Details |
| 1974 |
Detailed design |
Operative |
It. Lire: 9 b |
|
- CONSORZIO DI BONIFICA PELAU BUONCAMMINO (NU)
1. Water Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1967 |
General plan |
Approved |
It. Lire: 1,4 b |
|
2. Bau Enì and Su Scusorgiu Streams Management: lot I
| Year |
Task |
Stage |
Value of works |
Details |
| 1970 |
Detailed design, work supervision, book-keeping |
Operative |
It. Lire: 1 b |
|
2.1. Water Management: Lot II
| Year |
Task |
Stage |
Value of works |
Details |
| 1972-78 |
Detailed design, work supervision, book-keeping |
Operative |
It. Lire: 1,6 b |
|
3. Rio Pardu's Left Branches Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1974 |
Detailed design |
|
It. Lire: 150 m |
|
4. Rio Quirra Bridge and Roadway
| Year |
Task |
Stage |
Value of works |
Details |
| 1972 |
Detailed designs |
Operative |
It. Lire: 300 m |
|
6. Rio Quirra Valley Basin Localization
| Year |
Task |
Stage |
Value of works |
Details |
| 1979-86 |
Design |
|
|
|
6. Pelau River Bridge Renovation
| Year |
Task |
Stage |
Value of works |
Details |
| 1983-9378 |
Design, work direction |
Operative |
It. Lire: 1,5 b |
|
7. December 1993's Flood
| Year |
Task |
Stage |
Value of works |
Details |
| 1994 |
Report |
|
|
|
- CONSORZIO DI BONIFICA DEL CAMPIDANO DI ORISTANO (OR)
1. Oristano Area Irrigation and Networks Management
| Year |
Task |
Stage |
Value of works |
Details |
| 1973 |
Design |
Approved |
It. Lire: 26 b |
Prog. Spec. 13 Casmez |
2. Bennati, Babau Mattoni and S. Vero Congiu Areas Full Pipe Network
| Year |
Task |
Stage |
Value of works |
Details |
| 1975 |
Design |
Operative |
It. Lire: 13 b |
Irrigational area: Ha 3,000 |
- SOCIETA' BONIFICHE SARDE - ARBOREA
Santa Vittoria Dam on Tirso River Upgrading
| Year |
Task |
Stage |
Value of works |
Details |
| 1972 |
Detailed design |
|
It. Lire: 400 m |
|
- CONSORZIO INDUSTRIALE DELLA SARDEGNA CENTRALE
Cedrino Aqueduct Water Provision to Sologo Industrial Area
| Year |
Task |
Stage |
Value of works |
Details |
| 1977 |
Design |
Operative |
It. Lire: 6,5 b |
With: Tomasi, Sallusto, Coscarelli, civ. Eng. |
Regione Sicilia
- SNAMPROGETTI SUD - DATA ENGINEERING
Porto Empedocle Industrial Port and Roadway
| Year |
Task |
Stage |
Value of works |
Details |
| 1989-90 |
Design |
|
|
Town Plan on behalf of A.S.I. Agrigento |
- CONSORZIO DI BONIFICA DELLA PIANA DI CATANIA - (CT)
1. Catania Plain Irrigation Network
| Year |
Task |
Stage |
Value of works |
Details |
| 1958 |
Detailed design, consultancy |
Operative |
|
Irrigational area: Ha 3,000 Client: Impresa Cidonio |
2. Catania Plain Irrigation Network: Renovation and Espansion
| Year |
Task |
Stage |
Value of works |
Details |
| 1969 |
Consultancy |
Operative |
|
Irrigational area: Ha 25,000 |
1956 - 2025:
69 years
experience in water engineering
Complete geographical list
CESECO INTERNATIONAL s.r.l. - Professional and consulting services
Water engineering consulting firm in Rome, hydroelectric plants, dams and weirs, aqueducts and sewages
Via Lugnano in Teverina 9 - 00181 Roma | Tel.: +0039 06/7811891 | Fax: +0039 06/7801129 | e-mail: ceseco@ceseco-int.it